Use this button to switch between dark and light mode.

Share your feedback on this Case Opinion Preview

Thank You For Submiting Feedback!

Experience a New Era in Legal Research with Free Access to Lexis+

  • Case Opinion

Ampersand Chowchilla Biomass, LLC v. United States

Ampersand Chowchilla Biomass, LLC v. United States

United States Court of Appeals for the Federal Circuit

February 24, 2022, Decided

2021-1385

Opinion

HUGHES, Circuit Judge.

This is a tax case. Ampersand Chowchilla Biomass, LLC and Merced Power, LLC appeal a decision of the Court of Federal Claims denying their request for additional payments of Section 1603 grants under the American Recovery and Reinvestment Act of 2009. Because we agree with the Court of Federal Claims that the relevant power facilities did not meet the requirements of the statute, we affirm.

In 2007, California Biomass Fund I, LLC (CalBio) acquired two defunct facilities and began restoring them and upgrading them to biomass facilities, expecting the facilities to be operational in 2008.

Before CalBio acquired the facilities, Pacific Gas & Electric Company had entered into power-purchase agreements with the facilities' previous [*2]  owner. PG&E had agreed to purchase electricity when (1) the facilities achieved commercial operations and passed initial capacity tests, (2) PG&E received performance-assurance payments, and (3) the facilities received approval from the California Public Utilities Commission. CalBio assumed these power-purchase agreements, and CalBio and PG&E later amended the agreements to loosen their requirements. CalBio and PG&E also entered into interconnection agreements that required the facilities to pass pre-parallel testing, which ensures that the facilities can operate at the same frequency and in the same phase as the transmission grid so that the facilities do not damage the grid.

While renovating in 2007, CalBio secured Authority to Construct permits for the facilities. These permits allowed construction on the facilities and allowed the facilities to generate and sell electricity. The Authority to Construct permits could be converted into Permits to Operate after the facilities met certain conditions, like emissions tests. Biomass facilities, though, often have some difficulty passing environmental tests. So instead of shutting down biomass facilities at the first sign of noncompliance—which [*3]  could lead to agricultural waste being burned in open fields, causing more environmental pollution—the San Joaquin Valley Air Pollution Control District has a Notice of Violation process in which the District fines and oversees noncompliant facilities until they are brought back into compliance.

The Chowchilla and Merced facilities had their "initial fires" in April and July 2008, respectively. CalBio labeled the facilities "in operation" as of May 15, 2008 and August 23, 2008. And the facilities passed pre-parallel testing under the PG&E interconnection agreements on June 17, 2008 and August 24, 2008.

Read The Full CaseNot a Lexis Advance subscriber? Try it out for free.

Full case includes Shepard's, Headnotes, Legal Analytics from Lex Machina, and more.

2022 U.S. App. LEXIS 4958 *; __ F.4th __; 2022 WL 552030

AMPERSAND CHOWCHILLA BIOMASS, LLC, MERCED POWER, LLC, Plaintiffs-Appellants v. UNITED STATES, Defendant-Appellee

Prior History:  [*1] Appeal from the United States Court of Federal Claims in No. 1:14-cv-00841-MCW, Senior Judge Mary Ellen Cos-ter Williams.

Ampersand Chowchilla Biomass, LLC v. United States, 150 Fed. Cl. 620, 2020 U.S. Claims LEXIS 2260 (Oct. 30, 2020)

Disposition: AFFIRMED.

CORE TERMS

facilities, electricity, testing, power-purchase, environmental, assigned, permits, Construct, biomass, compliance, generating, selling, Treasury, levels, regulation, emissions, trial court, energy

Civil Procedure, Appeals, Standards of Review, Clearly Erroneous Review, Governments, Courts, Courts of Claims, De Novo Review, Authority to Adjudicate, Energy & Utilities Law, Financing, Investment Tax Credits, Tax Law, Federal Income Tax Computation, Credits, Legislation, Interpretation, Electric Power Industry, Electricity Distribution & Transmission, Electricity Generation