Use this button to switch between dark and light mode.

Share your feedback on this Case Opinion Preview

Thank You For Submiting Feedback!

Experience a New Era in Legal Research with Free Access to Lexis+

  • Case Opinion

Erdman Co. v. Phoenix Land & Acquisition, LLC

Erdman Co. v. Phoenix Land & Acquisition, LLC

United States Court of Appeals for the Eighth Circuit

March 29, 2011, Submitted; August 16, 2011, Filed

No. 10-2854

Opinion

 [*1116]  LOKEN, Circuit Judge.

Erdman Company ("Erdman") and Erdman Architecture & Engineering Company ("EAEC") filed this diversity action to foreclose a contractor's lien and an architect's and engineer's lien against Phoenix Land & Acquisition, LLC ("Phoenix Land"), and Phoenix Health, LLC ("Phoenix Health"), as owners of the property, and three financial institutions with recorded security interests in the property. Phoenix Land filed a counterclaim, asserting breach of contract, negligence, breach of implied warranty, breach of fiduciary relationship, and deceptive trade practices by Erdman, and negligence by EAEC. Erdman  [**2] and EAEC now appeal the district court's1 order denying their motion to compel arbitration of Phoenix Land's counterclaim. ] We have jurisdiction over an appeal from an interlocutory order "denying an application . . . to compel arbitration." 9 U.S.C. § 16(a)(1)(C). The district court held that Erdman waived the right to arbitrate by evidencing its intent to resolve the entire dispute through litigation. ] Reviewing the waiver determination de novo but the district court's underlying factual findings for clear error, we affirm. See Lewallen v. Green Tree Servicing, L.L.C., 487 F.3d 1085, 1090 (8th Cir. 2007) (standard of review).

Erdman, a Wisconsin-based contractor specializing in health care facilities, entered into a Design-Build Contract with Phoenix Land as Owner to design and build a one-story addition to a surgical center in Fort Smith, Arkansas. Section 12.2 of the Contract provided that "[a]ny controversy or claim arising out of or relating to this Contract or its breach not resolved by mediation, except for claims relating to Design-Builder's lien rights . . . shall  [**3] be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect." The Contract identified EAEC as a wholly- [*1117]  owned subsidiary of Erdman that would perform Erdman's obligations to provide Design Services for the project. The Contract was signed by Erdman's Executive Vice President on behalf of both Erdman and EAEC. Phoenix Health has an unexplained ownership interest in the project site but was not named or referred to in the Contract.

After work on the project began, Phoenix Land signed a series of change orders that altered the plans by adding a second floor "dead shell space" for future expansion and by allowing for the addition of a third floor at a later date. Excavation for the elevator included in the new plans went below the area covered by a geotechnical report prepared for the project and penetrated an abandoned mineshaft. A sinkhole developed, damaging completed work and delaying the project. Erdman demanded time and extra monies to remediate this allegedly unforeseen condition. Phoenix Land investigated, concluded Erdman was responsible for the sinkhole, and refused to make progress payments when  [**4] Erdman would not complete the project without additional funding. Erdman halted construction with the project not completed.

Read The Full CaseNot a Lexis Advance subscriber? Try it out for free.

Full case includes Shepard's, Headnotes, Legal Analytics from Lex Machina, and more.

650 F.3d 1115 *; 2011 U.S. App. LEXIS 16875 **

Erdman Company; Erdman Architecture & Engineering Company, Plaintiffs - Appellants, v. Phoenix Land & Acquisition, LLC; Phoenix Health, LLC; et al., Defendants - Appellees,

Subsequent History: Motion denied by Erdman Co. v. Phoenix Land & Acquisition, LLC, 2012 U.S. Dist. LEXIS 194047 (W.D. Ark., July 26, 2012)

Prior History:  [**1] Appeal from the United States District Court for the Western District of Arkansas.

CORE TERMS

arbitration, district court, counterclaim, right to arbitration, claim of a lien, litigate, unjust enrichment, sinkhole, lawsuit, parties

Business & Corporate Compliance, Arbitration, Federal Arbitration Act, Orders to Compel Arbitration, Civil Procedure, Appeals, Appellate Jurisdiction, Interlocutory Orders, Alternative Dispute Resolution, Waiver, Standards of Review, Clearly Erroneous Review, De Novo Review, Questions of Fact & Law, Scope, Contracts Law, Types of Contracts, Construction Contracts