Authored by Alison Cripps, Head of Workplace, In-House and Technology, Practical Guidance Privacy Awareness Week 2025: Australia's Bold Leap into a New Era of Privacy Law Australia has taken a bold...
As law firms navigate a highly competitive and evolving market, the need for technology that drives efficiency, reduces costs, and delivers exceptional client service has never been more crucial. A recent...
Q&A with Richard Douglas KC, Gerard Mullins KC, and Simon Grant Annotated Civil Liability Legislation - Queensland, 6th edition is the essential companion for practitioners engaged in the conduct of...
Q&A with Dr Greg Byrne and Dr Jacqui Horan Sexual Assault Trials: Challenges and Innovations offers a comprehensive examination of the systemic issues in sexual assault trials across common law jurisdictions...
The Total Economic Impact™ of LexisNexis® Lexis+ AI for Large Law Firms, a commissioned study conducted by Forrester Consulting on behalf of LexisNexis, May 2025, projects that large law firms could achieve...
The NSW government introduced new disclosure requirements for developers entering into off-the-plan contracts for residential developments from 1 December 2019. A Disclosure Statement is now required to be attached to a contract for sale that includes information such as sunset dates, whether development approval has been obtained and details of any strata scheme, community precinct or neighbourhood scheme the lot may form part of. The developer is also required to attach a number of prescribed documents, including a draft plan prepared by a registered surveyor, any proposed schedule of finishes and draft strata by-laws. In other states, there are varied requirements for attachments to the contract:
Over the course of the contractual relationship, vendors must notify purchasers of any changes that are made to “material particulars” that were previously disclosed. This may include changes to the draft plan, the by-laws or easements affecting the lot.
If a purchaser can show that they would not have entered into the contract had they been aware of the change and that they are materially prejudiced by the change, they are entitled to rescind a contract because of a change to a “material particular”. Provision also exists for a purchaser to claim compensation of up to 2% of the purchase price for the change, with arbitration offered as a dispute resolution mechanism.
As part of the new legislative regime, the cooling off period for off-the-plan contracts was extended to 10 business days and a new form has been produced by the Law Society of NSW for this purpose. From 2 June 2020, this new form must be used in all contracts for sale in NSW. This is now a significantly longer period than found in other states – three clear business days in Victoria; five business days in Queensland and two clear business days in South Australia.
The case of Liao v LNG Properties Pty Ltd [2019] NSWSC 1846; BC201912615 demonstrates the importance of specificity in contracts for off-the-plan developments. It also shows the pitfalls of a vendor entering into a new contract for sale with a replacement purchaser. The facts of this case relate to a period before the commencement of the new legislative regime in relation to disclosure of material particulars by developers, but are illustrative of the issues that can arise that the NSW legislature has attempted to address.
In 2016, a purchaser entered into an off-the-plan contract to purchase a residential apartment in Ashfield, NSW from a developer. During negotiations, the purchaser was shown promotional material by the agent showing an internal area of 75 sqm for the apartment. The contract was silent on the internal area of the apartment.
The contract was rescinded in 2018 and a new contract was entered into by the original purchaser’s partner, Ms. Li. The new contract enabled Ms. Li to rescind the contract if the internal area of the lot was reduced by more than 5%. As constructed, the apartment was 70.8 sqm, which was a reduction in area of more than 5% from the represented area of 75 sqm and Ms. Li rescinded the contract.
The court found that Ms. Li was entitled to rescind this contract and also that had the original purchaser’s contract remained afoot, he could have done the same for his contract.
This case is a good example of the way courts are likely to interpret contracts that are ambiguous. The courts generally will strive to give contracts a sensible and business-like meaning. It remains to be seen whether the new legislative regime will ameliorate these issues, but it would be prudent for practitioners to ensure that off-the-plan contracts are drafted clearly and specifically.
For more information in issues discussed above read, full articles Mandatory disclosure obligations for off-the-plan sales (2020) 35(3) APLB 46 and Off-the-plan contracts and unit size: a lesson on contract specificity (2020) 35(1&2) APLB 2 or subscribe to our Australian Property Law Bulletin.